4. A hydropower installation is to be located where the downstream water-surface elevation is 150 m below the water-surface elevation


4. A hydropower installation is to be located where the downstream water-surface elevation is 150 m below the water-surface elevation in the reservoir. The 1.5-m-diameter concrete-lined penstock is 300 m long and has an estimated roughness height of 17.5 mm (ks). When the flow rate through the system is 30 m3 s. Estimate the power that can be extracted from the system.