Case in Point 11.2: Global Cooling You are a systems analyst at Global Cooling, a leading manufacturer of air conditioning


Case in Point 11.2: Global Cooling You are a systems analyst at Global Cooling, a leading manufacturer of air conditioning units. You are leading a team that is developing a new production scheduling system. The project is now in the application development stage. Unit testing has been completed, and you are in the final stages of integration testing. Your supervisor, Ella Pham, is eager to implement the new application ahead of schedule and asked if you could trim system testing from two weeks to three days, and use a direct cutover method instead of the parallel changeover method that originally was planned. 1. What are the pros and cons of reducing the system test time