Exercise 07-7 Manufacturing: Direct labor and factory overhead budgets LO P1 Addison Co. budgets production of 2,850 units during the


Exercise 07-7 Manufacturing: Direct labor and factory overhead budgets LO P1 Addison Co. budgets production of 2,850 units during the second quarter. Other information is as follows: Direct labor Each finished unit requires 6 direct labor hours, at a cost of $9 per hour. Variable overhead Applied at the rate of $11 per direct labor hour. Fixed overhead Budgeted at $640,000 per quarter. 1. Prepare a direct labor budget. 2. Prepare a factory overhead budget.